Underfloor Heating in Screed
We recommend 65 mm of screed on top of the insulation. All installation work must comply with
current Building Regulations. Note that the screed drying time can be up to 4 to 6 weeks
before the underfloor heating system is operated.
The mixing valve needs to be set at minimum temperature when commissioning
the system. Rapid heating of the screed can cause cracking so increase the
temperature by 2 to 3 degrees every day to gently raise the floor temperature to
the desired setting.